Falls River Generating Station: QA, Safety Management & Project Coordination for Power Plant Upgrade |
|
|
|
Location: |
|
Falls River Generating Station near Prince Rupert, BC |
|
General scope of work: |
|
Serving as Project Controller, Gary Bashforth capably acted as the owner's representative at BC Hydro's Falls River Generating Station project. |
|
This project involved the upgrade, rebuild and automation of a 1930-vintage power generating station to unmanned status. |
|
Gary was responsible for field supervision, construction inspection, safety, and contract co-ordination and enforcement services. Gary also acted as Commissioning Co-ordinator, responsible for all start-up procedures and activities. |
|
|
Key activities: |
|
• |
Construction and safety management |
|
• |
Construction inspection |
|
• |
Commissioning coordination |
|
|
|
|
|